Ablutions Upgrade Program

The program focuses on enhancing the public toilet facilities across Rottnest Island, a crucial aspect of the visitor experience.

Overview

The Ablutions Upgrade Program involves both new constructions and refurbishments of existing ablution facilities, from the settlement out to West End. The initiative addresses the ageing infrastructure, with many facilities over 30 years old and requiring significant improvements.

Accessibility is a key focus of the program, ensuring facilities cater to all visitors. The program also incorporates aesthetic improvements to the surrounding landscapes, contributing to an overall better visitor experience.

The project has already seen the completion of facilities in several key areas, with future upgrades scheduled for other important locations.

Key benefits

Upgraded ablution facilities around the island
Improved visitor experience
Inclusion of accessible facilities where feasible
Inclusion of baby change and toddler facilities where feasible
Ongoing provision of visitor amenity that is both safe and meets visitor expectations

Key dates

Oliver Hill, Wadjemup Lighthouse, Visitor Centre, The Basin, West End and Geordie Bay, and Longreach Bay facilities have been completed. 

Expected completion dates for the ablution facilities to be delivered this year are: 

  • Narrow Neck – October 2024
  • Digby Drive – October 2024

Location

Various locations across the island

Contact and further information

All ablution facilities around the island are scheduled to be upgraded over the coming years and we will continue to update you as the capital works program is implemented. You can reach us at the following details to find out more about these projects. Our contact lines are open Monday to Friday, 8:30 am to 5 pm, excluding public holidays.

Funding

Rottnest Island Authority will adopt a phased capital funding approach to the upgrades in this project.
Start date
-
End date
2020
October 2024
Status
Current
Location
Various locations across the island
Funding
Rottnest Island Authority will adopt a phased capital funding approach to the upgrades in this project.