Ablutions Upgrade Program
Overview
Key benefits
Key dates
Oliver Hill, Wadjemup Lighthouse, Visitor Centre, The Basin, West End and Geordie Bay, and Longreach Bay facilities have been completed.
Expected completion dates for the ablution facilities to be delivered this year are:
- Narrow Neck – October 2024
- Digby Drive – October 2024
Location
![](/images/default-source/project-locations/location-map---ablution-blocks.tmb-fallback.webp?Culture=en&sfvrsn=721a55ac_1)
Works notices
Rottnest Island Authority is progressing the Ablution Facilities Upgrade Program, with facilities across the island scheduled to be upgraded over the coming years as part of the island’s capital works program.
Digby Drive, Settlement Mall Ablutions Upgrades
Commencing: Mid-April 2024
Completion: Mid-October 2024
Ablutions will be closed while works are in progress. Alternative ablution facilities are nearby.
Upgrades will include the following:
- New universal accessible toilet facilities
- New family room with baby change facilities and lounge area
- New energy efficient fixtures and fittings
- Upgrade of existing building with new finishes to wall, floor and ceiling
- Improvements to entrance and definition to pathways
- Shade shelters, bike racks and bin enclosures
Narrow Neck Ablutions Replacement and Precinct Upgrade
Commencing: Mid-April 2024
Completion: Mid-October 2024
The new Narrow Neck Precinct and ablutions will include:
- Construction of new ablution block with hybrid septic system
- New bin enclosure area with vehicle turnaround
- Bus stop improvements
- Recreation area with bitumen stabilised limestone hardstand, shelters and picnic tables, and new vegetation.
Note: Demolition of old toilets will not commence until new toilets are operational.