An update on the works taking place on the island and how they may impact your visit.

Works and service improvements are conducted periodically across Wadjemup / Rottnest Island

A range of projects are also currently underway to refresh and revitalise the island facilities. These works aim to enhance the visitor experience and to preserve the island long term.

Please refer to this list for updates on works taking place and how they may impact your visit.

For information on projects that are transforming the island, visit Significant Projects.

For further information on planning your visit to the island, visit rottnestisland.com.

Last updated: 20 December 2024

Commencing: 8 August 2024 
Completion: 25 February 2025 

As part of the Main Jetty refurbishment project, the jetty pavement will be reconstructed and sealed with asphalt.

The reconstruction of the pavement will be undertaken in eight different phases to ensure visitor access to the jetty will be maintained for most of the time.

Commencing: October 2024 
Completion: 23 December 2024 

Replacement of turf will be undertaken to enhance the aesthetic appeal and functional areas of key main settlement areas. Paving to occur under the fig tree adjacent to Indianic Boutique. No access will be blocked to visitors.

Commencing: 23 December 2024 
Completion: 23 December 2024 

Delivery and placement of 10ft sea container behind The Basin ablutions. The container will be utilised by Surf Life Saving WA for equipment storage and as a lunch room. To be delivered after first barge arrival with minimal disruption to visitors.

Commencing: 21 November 2024
Completion:
 January 2026

Wadjemup was used as an Aboriginal prison and forced labour camp between 1838 and 1931. State records indicate that 4,000 Aboriginal men and boys from Western Australia were imprisoned on the island, including in the Quod. Heritage conservation works will conserve the building. Aboriginal monitors will be on site throughout the works.

Conservation works are being undertaken to ensure the stabilisation of the buildings ahead of decisions on future use.

The Quod will be fenced off during works and there will be some noise during the works.

Commencing: June 2023

Completion: September 2025

New food and beverage, accommodation and conference facilities for The Lodge Wadjemup are in progress.

Redevelopment includes new accommodation and refurbishment of 109 rooms including 46 new rooms and refurbishment of 31 Boys Reformatory rooms and 32 Lakeside Villas.

In addition, new food and beverage facilities including a kiosk, conference and event facilities, pools and amenities are under construction.

Stage 1
Completion: Late December 2024
New restaurant and kiosk open and refurbishment of the Courtyard rooms and Lakeside Villas.

Stage 2
Completion: September 2025
New poolside villas and conference facilities.

  • Noise and additional vehicle movements may occur during The Lodge Wadjemup redevelopment.
  • To ensure minimal disruption to visitors and the environment, Boreham Way will be closed with access only to contractors.
  • Public access remains open on Kitson Street, Digby Drive and surrounding Garden Lake.
  • Increased traffic is expected along Digby Drive, Brand Way, Parker Point Road and surrounding the aerodrome.
  • Vehicles involved in the works will need to travel during construction hours, Monday to Saturday.

Commencing: 17 August 2024   
Completion: 28 March 2025 
 
The electrical network capacity on the island is being increased to support the expansion of the desalination plant and future developments. 

Cabling and electrical infrastructure works are part of the island-wide electrical network upgrades. Noise and heavy traffic will impact the fenced-off work areas.